One of three 400 MW Beacon campuses ringing Edmonton.
Electrical demand
400 MW
Grid connection
Capital cost
Not published
as announced
Operator
Beacon AI Centers
AI / high-performance computing
Last verified
September 22, 2026
Primary-source record
Beacon Harry Smith AI Hub is in Parkland County, in the Edmonton region of Alberta. Its status as of September 22, 2026 is proposed.
Beacon Harry Smith AI Hub is planned at 400 MW of electrical demand. Running continuously, that is enough electricity for roughly 486,800 Alberta homes, or 3.2% of the province's all-time record peak demand of 12,384 MW.
Beacon AI Centers. Power: grid connection. 400 MW AESO grid connection requested; between Keephills and Duffield.