Small mixed-use site in Lacombe County.
Electrical demand
20 MW
On-site natural gas
Capital cost
Not published
as announced
Operator
VL Energy & Amada Nowlitt Energy
Mixed AI and crypto
Last verified
September 22, 2026
Primary-source record
How the province lists this project in its Major Projects Inventory, refreshed daily.
November 1, 2026 · provincial inventory
Province now lists this project as under construction
stage Proposed → Under Construction
Data Centre West of Clive is in Lacombe County, in the Central Alberta of Alberta. Its status as of September 22, 2026 is proposed.
Data Centre West of Clive is planned at 20 MW of electrical demand. Running continuously, that is enough electricity for roughly 24,340 Alberta homes, or 0.2% of the province's all-time record peak demand of 12,384 MW.
VL Energy & Amada Nowlitt Energy (listed by the province as VL Energy and Amada Nowlitt Energy). Power: on-site natural gas. On-site natural gas, biofuel-capable.