A gigawatt-class gas-powered campus near Edson.
Electrical demand
930 MW
930 MW on-site generation plus a 74.9 MW grid tie
Capital cost
$20 billion
as announced
Operator
Emerald Energy Technologies
AI / high-performance computing
Last verified
September 22, 2026
Primary-source record
Malachite One Data Centre is in Yellowhead County, in the Central Alberta of Alberta. Its status as of September 22, 2026 is proposed.
Malachite One Data Centre is planned at 930 MW of electrical demand (930 MW on-site generation plus a 74.9 MW grid tie). Running continuously, that is enough electricity for roughly 1,131,810 Alberta homes, or 7.5% of the province's all-time record peak demand of 12,384 MW.
Emerald Energy Technologies. Power: grid + on-site generation. 930 MW of natural gas generation with a small grid connection.