What we know
- Power
- On-site natural gas. AUC-approved natural gas (50 × 1.2 MW units).
- Timeline
- Approved; partially built.
- In perspective
- Enough for ~73,020 homes · 0.5% of Alberta's record peak · 0.1× Calgary's average draw
Pathfinder Rocky 5 Bitcoin Mining — questions people ask
Where is Pathfinder Rocky 5 Bitcoin Mining?+
Pathfinder Rocky 5 Bitcoin Mining is in Clearwater County, in the Central Alberta of Alberta. Its status as of September 22, 2026 is approved.
How much power will Pathfinder Rocky 5 Bitcoin Mining use?+
Pathfinder Rocky 5 Bitcoin Mining is planned at 60 MW of electrical demand (10 MW installed as of 2025). Running continuously, that is enough electricity for roughly 73,020 Alberta homes, or 0.5% of the province's all-time record peak demand of 12,384 MW.
Who is building Pathfinder Rocky 5 Bitcoin Mining and how will it be powered?+
Pathfinder. Power: on-site natural gas. AUC-approved natural gas (50 × 1.2 MW units).